Our techniques apply when adding new structures: especially rock anchor, microfine cement, soil nailing, micropile installations for foundation support. We specialize in slope stabilization, anchors, permeation grouting, foundation repair and support, grouting, soil nails, rock drilling, micropile installations, and sinkholes. We use a problem-solving approach geotechnical architecture of buildings, bridges, water plants, sewage plants, tunnels, sinkholes, caisson, shoring, underpinning, agriculture, and roads construction. We are experienced in these applications: micro piles, sinkhole repair, permeation grouting, pressure grout, soil nails, chemical grouting, micropiles, compaction grout, and rock anchors. Our specialties are rock anchor, acrylamide and compaction grouting, mini piles, sinkhole repair, micropiles, acrylamide grouting, and soil nailing. We will continue to dedicate ourselves to excellence, including insurance mortgage, in our performance, in our integrity, and in our relationships with our customers. We will carefully weigh our decisions, actions, and results to make sure that we remain the most trusted name in the geotechnical contracting industry. Please visit our website http://www.rembco.com/. Add Concrete Construction URL

Driven Piles
JULY
1997
7-41
Check the lifting procedure to ensure that the pile is not overstressed at anytime during
picking.
Allowable Stress
PSI tension
= '
5 f
c
Measure piles and paint the necessary one foot marks so blow counts can be determined.
Check the ends of the piles. Prestressing steel should be flush with the pile head. The head
of the pile should be square.
With concrete piles, make sure the cushion blocks are maintained in good condition. If the
driving is hard, they may have to be changed once or twice per pile.
Steel Piles
If the piles are to be spliced, the Contractor must have a prequalified welder do the work. If
the welder has been performing similar type work on other Caltrans jobs and 12 months
have not elapsed since this work, the welder does not have to run a prequalification test.
Verification of the welder’s work record can be obtained by calling the Office of Materials
Engineering and Testing Services (METS) in Sacramento with the welder’s name and social
security number.
Some welders who are not listed with METS will have qualification tests that were per-
formed by a private testing laboratory. Prequalification can be accomplished in this
instance by forwarding a copy of the test reports to the nearest Transportation Laboratory
office where they will verify the welder’s qualifications.
If the welder does not meet either of the above requirements, a prequalification test will
have to be made. A review of the ANSI/AASHTO/AWS D1.1 Welding Code will outline the
requirements.
It is obvious that all of the aforementioned takes time. Hence, it is extremely important that
determination of welder qualification be made as early as possible. It should also be noted
that once the welding work has been completed on the job by the certified welder, the
Engineer should forward a copy of the work record to the Office of Materials Engineering
and Testing Services. This will help to maintain current records and hopefully save some-
one some time later on. Also keep in mind that just because a person holds a welding
certification, it does not mean you do not have to look at the welding work.