Sub Sections:
1
2
3
4
5
6
7
8
9
10
11
12
Pages:
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
Micro Piles |
Pressure Grouting |
Rock Anchors |
Permeation Grouting
Soil Nailing |
Compaction Grouting |
Micropiles |
Injection Grouting |
Chemical Grouting
Our
techniques apply when adding new structures:
especially
rock anchor,
microfine cement,
soil nailing,
micropile
installations for
foundation support.
We
specialize in
slope stabilization,
anchors,
permeation grouting,
foundation repair
and support,
grouting,
soil nails,
rock drilling,
micropile installations, and
sinkholes. We
use a
problem-solving approach geotechnical
architecture of buildings, bridges,
water plants, sewage plants, tunnels,
sinkholes,
caisson,
shoring,
underpinning,
agriculture, and
roads
construction. We
are experienced in these applications:
micro piles,
sinkhole repair,
permeation grouting, pressure
grout,
soil nails,
chemical grouting,
micropiles,
compaction grout, and
rock anchors.
Our specialties are
rock anchor,
acrylamide and
compaction grouting,
mini piles,
sinkhole repair,
micropiles,
acrylamide grouting, and
soil nailing.
We will continue to dedicate ourselves to
excellence,
including
insurance mortgage, in our performance, in our
integrity, and in our relationships with our
customers. We will carefully weigh our
decisions, actions, and results to make sure
that we remain the most trusted name in the
geotechnical contracting industry. Please
visit our website
http://www.rembco.com/.
Add Concrete Construction URL
Artistic Business Community Related Construction Industry Computers Education Relevant Entertainment Health Internet Family Recreation Science Shopping Society
|

Slurry Displacement Piles
JULY
1997
9-43
During construction, do not permit the use of drilling slurries or chemical additives for
which a MSDS has not been submitted.
Specifications
Because of the nature of slurry displacement construction, visual inspection of the drilled
shaft is not possible for much of the time. Most of the drilling and concrete placement is
done “in the blind”. As a result, the contract specifications for this work, which were revised
in 1994, are quite stringent in an attempt to minimize the risks and to ensure that the pile
has structural and geotechnical integrity. Some of the more critical requirements of the
contract specifications are discussed in the following sections.
Minimum Pile Diameter Requirements
Only piles 24 inches in diameter or greater may be constructed by the slurry displacement
method. This is because a pile with a lesser diameter may not contain enough room for the
rebar cage, inspection tubes, and the large concrete delivery tubes. If a contract specifies the
use of piles with a diameter of less than 24 inches, the Contractor may propose to increase
the diameter of the pile to at least 24 inches by the provisions described in Section 49-4.03
of the Standard Specifications if use of the slurry displacement method of construction is
desired. However, the diameter of the rebar cage would have to be increased from the
original size in order to accommodate the items mentioned above.
Pile Placing Plan Requirements
Before any pile construction work using the slurry displacement method can begin, the
Contractor shall submit a detailed placing plan to the Engineer for approval. The placing
plan is necessary to show that the Contractor has thought out what needs to be done during
the construction process, has a plan for addressing all aspects of the work, and can show
that the pile can be constructed in a timely manner. Because the contract specifications
state that the Contractor shall place the concrete for a single pile within a two hour period,
the Contractor must be able to show that the equipment, including concrete pumps and
delivery tubes, will be adequate to meet this requirement. The Contractor must also show
that the delivery rate from the concrete supplier will be adequate to meet this requirement.
The intent of this specification is to limit the amount of time in which suspended materials
can settle out of the drilling slurry during concrete placement and to make sure the