Installing Standpipe Piezometer in Borehole
1
Flush borehole with clean water. Attach filter tip to pipe. Add additional lengths of pipe as standpipe
is lowered into borehole, sealing joints with tape or glue. Continue adding pipe until tip has reached
required depth.
2
Place sand around tip using tremie pipe. Sand must be wet to tremie successfully.
3
Place bentonite seal. Drop pellets or chips into borehole slowly to avoid bridging. Use of flush cou-
pled pipe also helps to prevent bridging. Add water as needed for hydration of bentonite. Allow time
for bentonite to swell.
4
Fill remainder of borehole with bentonite or bentonite-cement grout.
5
Cut standpipe to length. Top off borehole with grout and install protective cover. Hand over to client
after proving installation.
Piezometers
Rembco Geotechnical Contractors specializes in
slope stabilization,
soil nail wall,
foundation repair
and support,
grouting,
shoring,
micropile
construction,
rock drilling, and we remediate
sinkholes. We use a
problem-solving approach in the geotechnical portions of buildings, bridges, water plants, sewage plants, tunnels,
installing caisson bottom, and roads. We are experienced in these applications:
micro piles,
sinkhole repair,
permeation and
pressure
grouting,
soil nails,
cement grouting,
chemical grouting,
micropiles,
compaction grouting, and
rock anchors.
Rembco techniques apply when adding new structures: especially
rock anchor,
microfine cement,
soil nailing, and
micropile
installations for foundation support. Our specialties are
soil nails,
rock anchor,
chemical and
compaction grouting,
mini piles,
sinkhole repair,
micropiles, and
soil nailing.