Using Tremied Grout
1
Clear drilling mud and debris from borehole. Attach bottom cap to bottom section of casing.
2
Install casing in borehole, adding casing sections as necessary until casing reaches specified depth. In
water-filled boreholes, fill casing with water to counter buoyancy. In dry boreholes, install dry casing.
Fill casing with water to counter buoyancy when grouting begins. Keep water at same level as grout to
avoid disturbing sealed couplings.
3
Lower steel bar or pipe to bottom of casing to counteract buoyancy while grout sets. Then lower grout
pipe to bottom of borehole and pump in grout.
4
Top off borehole with grout and install protective cover. Take initial readings, then hand over to client.
Inclinometers
Rembco Geotechnical Contractors specializes in
slope stabilization,
soil nail wall,
foundation repair
and support,
grouting,
shoring,
micropile
construction,
rock drilling, and we remediate
sinkholes. We use a
problem-solving approach in the geotechnical portions of buildings, bridges, water plants, sewage plants, tunnels,
installing caisson bottom, and roads. We are experienced in these applications:
micro piles,
sinkhole repair,
permeation and
pressure
grouting,
soil nails,
cement grouting,
chemical grouting,
micropiles,
compaction grouting, and
rock anchors.
Rembco techniques apply when adding new structures: especially
rock anchor,
microfine cement,
soil nailing, and
micropile
installations for foundation support. Our specialties are
soil nails,
rock anchor,
chemical and
compaction grouting,
mini piles,
sinkhole repair,
micropiles, and
soil nailing.