Installation
Magnetic Extensometers
1
Flush debris from borehole. Fix datum magnet to bottom section of access pipe. Number other
sections of pipe for installation. Fix spider magnets to each section. Label release cords, coil, and tape
to pipe.
2
Attach grout hose to bottom section of pipe. Lower pipe into borehole. Add next section of pipe. Seal
pipe joint. Carefully remove safety ties from magnet legs, then push pipe into borehole. Arrange
release cord so legs are not released accidentally. Add additional sections of pipe as required. Check
magnet depths.
3
Begin grouting. Release magnet legs as level of grout rises. If drill casing used, pull casing before
releasing legs. Continue until all spider magnets are released and borehole is filled with grout.
4
Terminate as specified. Obtain good initial readings, then hand over to client.
Rembco Geotechnical Contractors specializes in
slope stabilization,
soil nail wall,
foundation repair
and support,
grouting,
shoring,
micropile
construction,
rock drilling, and we remediate
sinkholes. We use a
problem-solving approach in the geotechnical portions of buildings, bridges, water plants, sewage plants, tunnels,
installing caisson bottom, and roads. We are experienced in these applications:
micro piles,
sinkhole repair,
permeation and
pressure
grouting,
soil nails,
cement grouting,
chemical grouting,
micropiles,
compaction grouting, and
rock anchors.
Rembco techniques apply when adding new structures: especially
rock anchor,
microfine cement,
soil nailing, and
micropile
installations for foundation support. Our specialties are
soil nails,
rock anchor,
chemical and
compaction grouting,
mini piles,
sinkhole repair,
micropiles, and
soil nailing.