Installation of VWP Spot-Weldable Strain Gauge
1
Prepare surface: Remove rust with sander. If necessary, create a
flat surface with grinder. Check that surface is clean.
2
Weld gauge to surface, as shown in drawing. Hold insulating card
between welding tip and tube to prevent welding damage.
3
Apply corrosion protection to gauge (3M Scotch Kote).
4
Mount strain gauge sensor on top of strain gauge. If the gauge is
on rebar, use plastic tie-wraps to secure sensor. Then wrap mastic
pad around sensor and gauge. Finally, wrap self-vulcanizing tape
over the entire assembly.
If gauge is on beam, place tie-down straps over sensor and weld
to beam. Do not allow contact between welder tip and sensor.
Weld protective cover over installation. Fit mastic pad over pro-
tective cover and exit point of cable.
Strain Gauges
Start Welds in Center, Work Toward End.
Place Insulating Card Between Tube and
Welder Tip to Protect Tube.
3rd Row
2nd Row
1st Row
.05"
(3 Rows Per Side)
0.1"
V WGA U GE .c dr
Note: Spot Weld as Close
to Ends as Possible.
Rembco Geotechnical Contractors specializes in
slope stabilization,
soil nail wall,
foundation repair
and support,
grouting,
shoring,
micropile
construction,
rock drilling, and we remediate
sinkholes. We use a
problem-solving approach in the geotechnical portions of buildings, bridges, water plants, sewage plants, tunnels,
installing caisson bottom, and roads. We are experienced in these applications:
micro piles,
sinkhole repair,
permeation and
pressure
grouting,
soil nails,
cement grouting,
chemical grouting,
micropiles,
compaction grouting, and
rock anchors.
Rembco techniques apply when adding new structures: especially
rock anchor,
microfine cement,
soil nailing, and
micropile
installations for foundation support. Our specialties are
soil nails,
rock anchor,
chemical and
compaction grouting,
mini piles,
sinkhole repair,
micropiles, and
soil nailing.