Micro Piles  |  Pressure Grouting  |  Rock Anchors  |  Permeation Grouting   |  Micropile
Soil Nailing  |  Compaction Grouting  |  Micropiles  |  Chemical Grouting   |  Soil Nail Wall


General Construction Specifications

    SECTION 02514

    PORTLAND CEMENT CONCRETE PAVING

   PART 1 - GENERAL

   1.01 SECTION INCLUDES

    A. Extent of Portland cement concrete paving is as required for restoration, including curbs, gutters, walks and pavement.

   1.02 QUALITY ASSURANCE

    A. Codes and Standards: Comply with local governing regulations if more stringent than herein specified.

   1.03 REFERENCE STANDARDS

    A. ASTM A184 - Specifications for Fabricated Deformed Steel Bar Mats for Concrete Reinforcement.

    B. ASTM A185 - Specifications for Steel Welded Wire Fabric, Plain, for Concrete Reinforcement.

    C. ASTM A307 - Specifications for Carbon Steel Bolts and Studs, 6,000 psi Tensile.

    D. ASTM C615 - Specifications for Deformed and Plain Billet Steel Bars for Concrete Reinforcement.

    E. ASTM C33 - Specifications for Concrete Aggregates.

    F. ASTM C150 - Specifications for Portland Cement.

    G. ASTM C309 - Specifications for Liquid Membrane-Forming Compounds for Curing Concrete.

   1.04 SUBMITTALS

    A. Furnish samples, manufacturer's product data, test reports, and materials' certifications as required to demonstrate compliance with specifications.

   1.05 JOB CONDITIONS

    A. Traffic Control: Maintain access for vehicular and pedestrian traffic as required for other construction activities.

    B. Utilize flagmen, barricades, warning signs and warning lights as required.

   PART 2 - PRODUCTS

   2.01 MATERIALS

    A. Forms: Steel, wood, or other suitable material of size and strength to resist movement during concrete placement and to retain horizontal and vertical alignment until removal. Use straight forms, free of distortion and defects.

    B. Use flexible spring steel forms or laminated boards to form radius bends as required.

    C. Coat forms with a non-staining form release agent that will not discolor or deface surface of concrete.

    D. Welded Wire Mesh: Welded plain cold-drawn steel wire fabric, ASTM A 185.

    1. Furnish in flat sheets, not rolls, unless otherwise acceptable to Engineer.

    E. Reinforcing Bars: Deformed steel bars, ASTM A 615, Grade 60.

    F. Fabricated Bar Mats: Welded or clip-assembled steel bar or rod mats, ASTM A184. Use ASTM A615, Grade 60 steel bars, unless otherwise indicated.

    G. Joint Dowel Bars: Plain steel bars, ASTM A 615, Grade 60. Cut bars true to length with ends square and free of burrs.

    H. Metal Expansion Caps: Furnish for one end of each dowel bar in expansion joints. Design caps with one end closed and a minimum length of 3" to allow bars movement of not less than 1", unless otherwise indicated.

    I. Hook Bolts: ASTM A 307, Grade A bolts, internally and externally threaded. Design hook bolt joint assembly to hold coupling against pavement form and in position during concreting operations, and to permit removal without damage to concrete or hook bolt.

    J. Concrete Materials: Comply with requirements of applicable Division 3 sections for concrete materials, admixtures, bonding materials, curing materials, and others as required.

    K. Concrete Materials:

    1. Portland Cement: ASTM C150, Type 1, unless otherwise acceptable to Engineer.

    2. Normal Weight Aggregates: ASTM C33 except, local aggregates not complying with ASTM C33 but which have shown by special test or actual service to produce concrete of adequate strength and durability may be used when acceptable to Engineer.

    3. Water: Potable.

    4. Admixtures: As authorized by Engineer.

    L. Expansion Joint Materials: Comply with requirements of applicable Division 7 sections for preformed expansion joint fillers and sealers.

    M. Expansion Joint Material: Preformed expansion joint fillers and sealers; size and locations as shown on drawings; installed in accordance with manufacturer's recommendations for intended use.

    N. Anti-Spalling Compound: 50% (by volume) boiled linseed oil and 50% (by volume) mineral spirits, complying with AASHTO M-233.

    O. Liquid-Membrane Forming Curing Compound: Complying with ASTM C-309, Type I, Class A unless other type acceptable to Engineer. Moisture loss not more than 0.055 gr./sq. cm. when applied at 200 sq. ft./gal.

    1. Products: Subject to compliance with requirements, provide one of the following:

    a) "Masterseal"; Master Builders.

    b) "A-H 3 Way Sealer"; Anti-Hydro Waterproofing Co.

    c) "Ecocure"; Euclid Chemical Co.

    d) "Clear Seal"; A.C. Horn.

    e) "J-20 Acrylic Cure"; Dayton Superior.

    f) "Sure Cure"; Kaufman Products Inc.

    g) "Spartan-Cote"; The Burke Co.

    h) "Sealkure"; Toch Div. - Carboline.

    i) "Kure-N-Seal"; Sonneborn-Contech.

    j) "Polyclear"; Upco Chemical/USM Corp.

    k) "L&M Cure"; L & M Construction Chemicals.

    l) "Klearseal"; Setcon Industries.

    m) "LR-152"; Protex Industries.

    n) "Hardtop"; Gifford - Hill.

    P. Bonding Compound: Polyvinyl acetate or acrylic base, rewettable type.

    1. Products: Subject to compliance with requirements, provide one of the following:

    a) "J-40 Bonding Agent"; Dayton Superior Corp.

    b) "Weldcrete"; Larsen Products.

    c) "Everbond"; L & M Construction Chemicals.

    d) "EucoWeld"; Euclid Chemical Co.

    e) "Hornweld"; A.C. Horn

    f) "Sonocrete"; Sonneborn-Contech.

    g) "Acrylic Bondcrete"; The Burke Co.

    Q. Epoxy Adhesive: ASTM C-881, two component material suitable for use on dry or damp surfaces. Provide material "Type", "Grade", and "Class" to suit project requirements.

    1. Products: Subject to compliance with requirements, provide one of the following:

    a) "Epoxtite"; A.C. Horn.

    b) "Edoco 2118 Epoxy Adhesive"; Edoco Technical Prod.

    c) "Sikadur Hi-Mod"; Sika Chemical Corp.

    d) "Euco Epoxy 463 or 615"; Euclid Chemical Co.

    e) "Patch and Bond Epoxy"; The Burke Co.

    f) "Sure-Poxy"; Kaufman Products Inc.

   2.02 CONCRETE MIX, DESIGN AND TESTING

    A. Comply with requirements of applicable sections for concrete mix design, sampling and testing, and quality control, and as herein specified.

    B. Design mix to produce normal-weight concrete consisting of Portland cement, aggregate, water-reducing or high-range water reducing admixture (super-plasticizer), air-entraining admixture and water to produce the following properties:

    1. Compressive Strength: 3500 psi, minimum at 28 days, unless otherwise indicated.

    2. Slump Range: 8" for concrete containing HRWR admixture (super-plasticizer); 3" for other concrete.

    3. Air Content: 5% to 8%.

   PART 3 - EXECUTION

   3.01 SURFACE PREPARATION

    A. Remove loose material from compacted subbase surface immediately before placing concrete.

    B. Proof-roll prepared subbase surface to check for unstable areas and need for additional compaction. Do not begin paving work until such conditions have been corrected and are ready to receive paving.

   3.02 FORM CONSTRUCTION

    A. Set forms to required grades and lines, rigidly braced and secured. Install sufficient quantity of forms to allow continuous progress of work and so that forms can remain in place at least 24 hours after concrete placement.

    B. Check completed formwork for grade and alignment to following tolerances:

    1. Top of forms not more than 1/8" in 10'.

    2. Vertical face on longitudinal axis, not more than 1/4" in 10'.

    C. Clean forms after each use, and coat with form release agent as often as required to ensure separation from concrete without damage.

   3.03 REINFORCEMENT

    A. Locate, place and support reinforcement as specified in Division 3 sections, unless otherwise indicated.

   3.04 CONCRETE PLACEMENT

    A. Do not place concrete until subbase and forms have been checked for line and grade. Moisten subbase if required to provide a uniform dampened condition at time concrete is placed. Do not place concrete around manholes or other structures until they are at required finish elevation and alignment.

    B. Place concrete using methods which prevent segregation of mix. Consolidate concrete along face of forms and adjacent to transverse joints with internal vibrator. Keep vibrator away from joint assemblies, reinforcement, or side forms. Use only square-faced shovels for hand-spreading and consolidation. Consolidate with care to prevent dislocation of reinforcing, dowels, and joint devices.

    C. Use bonding agent at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.

    D. Deposit and spread concrete in a continuous operation between transverse joints, as far as possible. If interrupted for more than 1/2-hour, place a construction joint.

    E. When adjacent pavement lanes are placed in separate pours, do not operate equipment on concrete until pavement has attained sufficient strength to carry loads without injury.

    F. Fabricated Bar Mats: Keep mats clean and free from excessive rust, and handle units to keep them flat and free of distortions. Straighten bends, kinks, or other irregularities or replace units as required before placement. See mats for a minimum 2" overlap to adjacent mats.

    G. Place concrete in 2 operations; strike-off initial pour for entire width of placement and to the required depth below finish surface. Lay fabricated bar mats immediately in final position. Place top layer in concrete, strike-off and screed.

    1. Remove and replace portions of bottom layer of concrete which has been placed more than 15 minutes without being covered by top layer or use bonding agent if acceptable to Engineer.

    H. Curbs and Gutters: Automatic machine may be used for curb and gutter placement at Contractor's option. If machine placement is to be used, submit revised mix design and laboratory test results which meet or exceed minimums specified. Machine placement must produce curbs and gutters to required cross-section, lines, grades, finish, and jointing as specified for formed concrete. If results are not acceptable, remove and replace with formed concrete as specified.

   3.05 JOINTS

    A. General: Construct expansion, weakened-plane (contraction), and construction joints true-to-line with face perpendicular to surface of concrete. Construct transverse joints at right angles to the centerline, unless otherwise indicated.

    B. When joining existing structures, place transverse joints to align with previously placed joints, unless otherwise indicated.

    C. Weakened-Plane (Contraction) Joints: Provide weakened-plane (contraction) joints, sectioning concrete into areas as shown on drawings. Construct weakened-plane joints for a depth equal to at least 1/4 concrete thickness, as follows:

    1. Tooled Joints: Form weakened-plane joints in fresh concrete by grooving top portion with a recommended cutting tool and finishing edges with a jointer.

    2. Sawed Joints: Form weakened-plane joints using powered saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut joints into hardened concrete as soon as surface will not be torn, abraded, or otherwise damaged by cutting action.

    3. Inserts: Use embedded strips of metal or sealed wood to form weakened-plane joints. Set strips into plastic concrete and carefully remove strips after concrete has hardened.

    D. Construction Joints: Place construction joints at the end of placements and at locations where placement operations are stopped for a period of more than 1/2 hour, except where such placements terminate at expansion joints.

    1. Construct joints as shown or, if not shown, use standard metal keyway-section forms.

    2. Where load transfer-slip dowel devices are used, install so that one end of each dowel bar is free to move.

    E. Expansion Joints: Provide premolded joint filler for expansion joints abutting concrete curbs, catch basins, manholes, inlets, structures, walks and other fixed objects, unless otherwise indicated.

    1. Locate expansion joints at 50' o.c. for each pavement lane, unless otherwise indicated.

    F. Extend joint fillers full-width and depth of joint, and not less than 1/2" or more than 1" below finished surface where joint sealer is indicated. If no joint sealer, place top of joint filler flush with finished concrete surface.

    G. Furnish joint fillers in one-piece lengths for full width being placed, wherever possible. Where more than one length is required, lace or clip joint filler sections together.

    H Protect top edge of joint filler during concrete placement with a metal cap or other temporary material. Remove protection after concrete has been placed on both sides of joint.

    I. Fillers and Sealants: Comply with the requirements of applicable Division 7 sections for preparation of joints, materials, installation, and performance.

   3.06 CONCRETE FINISHING

    A. After striking-off and consolidating concrete, smooth surface by screeding and floating. Use hand methods only where mechanical floating is not possible. Adjust floating to compact surface and produce uniform texture.

    B. After floating, test surface for trueness with a 10' straightedge. Distribute concrete as required to remove surface irregularities, and refloat repaired areas to provide a continuous smooth finish.

    C. Work edges of slabs, gutters, back top edge of curb, and formed joints with an edging tool, and round to 1/2" radius, unless otherwise indicated. Eliminate tool marks on concrete surface.

    D. After completion of floating and troweling when excess moisture or surface sheen has disappeared, complete surface finishing, as follows:

    1. Broom finish, by drawing a fine-hair broom across concrete surface, perpendicular to line of traffic. Repeat operation if required to provide a fine line texture.

    E. Do not remove forms for 24 hours after concrete has been placed. After form removal, clean ends of joints and point-up any minor honeycombed areas. Remove and replace areas or sections with major defects, as directed by Engineer.

   3.07 CURING

    A. Use membrane-forming curing and sealing compound or approved moist-curing methods in accordance with manufacturer's recommendations.

    B. Do not use liquid membrane-forming materials where anti-spalling treatment will be applied.

    C. Anti-Spalling Treatment: A second coat of curing and sealing compound may be used or an anti-spalling compound applied over concrete cured by continuous moist curing methods. Apply compounds to concrete surfaces no sooner than 28 days after placement, to clean, dry concrete free of oil, dirt, and other foreign material. Apply curing and sealing compound at a maximum coverage rate of 300 sq. ft./gallon. Apply anti-spalling compound in two sprayed applications. First application at rate of 40 sq. yds. per gal.; second application, 60 sq. yds. per gallon. Allow complete drying between applications.

   3.8 REPAIRS AND PROTECTIONS

    A. Repair or replace broken or defective concrete, as directed by Engineer.

    B. Drill test cores where directed by Engineer, when necessary to determine magnitude of cracks or defective areas. Fill drilled core holes in satisfactory pavement areas with portland cement concrete bonded to pavement with epoxy adhesive.

    C. Protect concrete from damage until acceptance of work. Exclude traffic from pavement for at least 14 days after placement. When construction traffic is permitted, maintain pavement as clean as possible by removing surface stains and spillage of materials as they occur.

    D. Sweep concrete pavement and wash free of stains, discolorations, dirt and other foreign material just prior to final inspection.

   3.9 Exposed Aggregate

    A. Wash exposed aggregate surface with acid etch solution exposing aggregate to match existing concrete paving.

    END OF SECTION

This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 6 7 8 9 10 11 13 14 15 16

Rembco Geotechnical Contractors specializes in slope stabilization, foundation repair and support, shoring, grouting, soil nails, micropile installations, and sinkholes. We are experienced in these applications: micro piles, sinkhole repair, permeation grouting, pressure grouting, soil nails, chemical grouting, micropiles, compaction grout, rock anchors and compaction piles. Our specialties are rock anchor, chemical and compaction grouting, mini piles, sinkhole repair, micropiles, and soil nailing. We use a problem-solving approach in the geotechnical portions of buildings, bridges, water plants, sewage plants, tunnels, sinkholes, caisson, and roads. Rembco techniques apply when adding new real estate structures: especially rock anchor, microfine grouting, soil nailing, micropile installations for foundation support. Add URL Construction, Drilling and Concrete